Canal Dredging Update – Friday, February 1, 2019

The dredge project is almost complete as there is about 400-feet left to dredge to the end of the DeBordieu canal.  We anticipate this section will be complete by tomorrow afternoon.

The crew will begin to dismantle the pipe on Monday, February 4 and head to the boat landing and Debidue Creek to perform some minor touch-ups.

The Army Corps of Engineers has extended the dredging completion deadline to February 15, 2019.